The Commission on Audit (CoA) has filed four Fraud Audit Reports (FARs) before the Office of the Ombudsman involving more than P275 million worth of flood controlThe Commission on Audit (CoA) has filed four Fraud Audit Reports (FARs) before the Office of the Ombudsman involving more than P275 million worth of flood control

CoA files 4 Fraud Audit Reports worth over P275 million for Bulacan flood control projects; flags ghost projects, unauthorized relocations, and questionable accomplishments

2026/02/16 11:21
4 min read

The Commission on Audit (CoA) has filed four Fraud Audit Reports (FARs) before the Office of the Ombudsman involving more than P275 million worth of flood control projects in Bulacan, citing alleged ghost projects, unauthorized site relocations, payments for pre-existing structures, and serious documentation deficiencies.

The projects were implemented by the Department of Public Works and Highways (DPWH)-Bulacan 1st District Engineering Office and awarded to SYMS Construction Trading and Wawao Builders.

The CoA said the filing of the cases underscores its commitment to transparency and accountability to ensure that public funds intended for flood mitigation are properly used.

Based on physical inspections, geotagged photographs, and historical satellite imagery, state auditors reported recurring irregularities:

Ghost projects: No flood control or riverbank protection structures were found at approved project sites, despite reports that the projects were completed or substantially accomplished.

Unauthorized relocation of sites: In several instances, DPWH representatives allegedly led inspectors to locations different from those specified in approved plans and contracts, without revised plans or written authority.

Payments for preexisting structures: Satellite imagery showed that some riverbank protection structures already existed prior to contract effectivity, raising the possibility that payments were made for works not newly constructed.

Documentation deficiencies: Required documents, including as-built plans, detailed cost breakdowns, Statements of Work Accomplished, and approved master plans, were either incomplete or missing, undermining the credibility of reported accomplishments and payments.

Audit Coverage

The fraud audit stemmed from a directive issued on Aug. 12, 2025 by CoA Chairperson Gamaliel A. Cordoba ordering an immediate review of DPWH flood control projects in Bulacan covering July 1, 2022 to May 30, 2025, following public concerns over alleged ghost projects and corruption.

Disputed Projects

Hagonoy, Bulacan (SYMS Construction Trading)

The P67.55-million project involved the construction of a reinforced concrete flood control structure at Barangay Santa Monica (Purok 6 to Purok 7). The CoA reported that no such structure was found at the designated site despite the project being declared 100% complete as of June 11, 2024 and fully paid by June 19, 2024. Auditors also noted indications of unauthorized site changes and missing required documents.

Pandi, Bulacan (SYMS Construction Trading)

The P39.60-million riverbank protection project at Barangay Malibong Bata was allegedly built at a location different from that specified in approved engineering plans, without documented authority for relocation. Structures found at both the approved and identified sites could not be conclusively linked to the contract. Several key documents were also missing.

Baliuag, Bulacan (Wawao Builders)

The P72.37-million Phase IV riverbank protection project at Barangay San Roque was reportedly constructed at a site different from that indicated in the approved bid plans. The structure bore markings corresponding to another project. Geotagged progress photos used to support payments were taken before the issuance of the Notice to Proceed and pointed to a different barangay. The CoA also cited overlapping project locations with another flood control contract and incomplete documentation.

Plaridel, Bulacan (Wawao Builders)

The P96.50-million flood control structure along the Angat River in the Lumang Bayan section was found to have existing structures at the site at least 90 days before contract effectivity, based on satellite imagery and inspection. The structures bore markings of different contract IDs and differed in design from approved plans. Despite this, the project was reported 100% complete within 65 days from contract effectivity. Auditors again noted missing supporting documents.

Possible Violations

The CoA said those involved may face charges for violations of Republic Act No. 3019, or the Anti-Graft and Corrupt Practices Act, as well as malversation and falsification of documents under the Revised Penal Code. Possible violations of COA Circular No. 2009-001 were also cited.

The audit body said additional reports may be filed with the Ombudsman as investigations continue, in line with President Ferdinand R. Marcos, Jr.’s call for transparency and accountability in government spending.


Spotlight is BusinessWorld’s sponsored section that allows advertisers to amplify their brand and connect with BusinessWorld’s audience by publishing their stories on the BusinessWorld Web site. For more information, send an email to online@bworldonline.com.

Join us on Viber at https://bit.ly/3hv6bLA to get more updates and subscribe to BusinessWorld’s titles and get exclusive content through www.bworld-x.com.

Market Opportunity
Alliance Games Logo
Alliance Games Price(COA)
$0.001114
$0.001114$0.001114
+2.20%
USD
Alliance Games (COA) Live Price Chart
Disclaimer: The articles reposted on this site are sourced from public platforms and are provided for informational purposes only. They do not necessarily reflect the views of MEXC. All rights remain with the original authors. If you believe any content infringes on third-party rights, please contact service@support.mexc.com for removal. MEXC makes no guarantees regarding the accuracy, completeness, or timeliness of the content and is not responsible for any actions taken based on the information provided. The content does not constitute financial, legal, or other professional advice, nor should it be considered a recommendation or endorsement by MEXC.
Tags:

You May Also Like

Tests 50-day EMA barrier near 183.00

Tests 50-day EMA barrier near 183.00

The post Tests 50-day EMA barrier near 183.00 appeared on BitcoinEthereumNews.com. EUR/JPY remains steady after three days of gains, trading around 182.70 during
Share
BitcoinEthereumNews2026/02/23 17:03
Shapeshift Founder’s Strategic $20.38 Million Bet Signals Renewed Confidence

Shapeshift Founder’s Strategic $20.38 Million Bet Signals Renewed Confidence

The post Shapeshift Founder’s Strategic $20.38 Million Bet Signals Renewed Confidence appeared on BitcoinEthereumNews.com. Ethereum Purchase: Shapeshift Founder
Share
BitcoinEthereumNews2026/02/23 16:57
BDACS rolls out KRW1 stablecoin backed by Woori Bank PoC

BDACS rolls out KRW1 stablecoin backed by Woori Bank PoC

The post BDACS rolls out KRW1 stablecoin backed by Woori Bank PoC appeared on BitcoinEthereumNews.com. In this post: BDACS has launched KRW1 stablecoin, which is backed by the South Korean won, after completing a full proof of concept with Woori Bank. The firm has also developed issuance and management systems and a user-facing app that supports P2P transfers and transaction verification. BDACS believes banking API integration will ensure transparent, verifiable proof of reserves and reinforce trust and accountability within its network. BDACS officially launched a South Korean won-backed stablecoin, KRW1, on Wednesday. The initiative comes after the company completed a full proof of concept (PoC) with Woori Bank. The company acknowledged that the milestone marks the interaction of fiat deposits, stablecoin issuance, and blockchain verification into a fully operational ecosystem. The firm also revealed that KRW1 is a proprietary stablecoin brand it trademarked in December 2023.  BDACS develops issuance and management systems BDACS said it anticipated the central role of stablecoins in the digital asset economy and started building the necessary infrastructure well before formal regulations were in place. The Korean firm stated that its Go-to-Market strategy has positioned it as a first mover in the region’s evolving digital asset market. According to the report, the initiative extends beyond token issuance. The digital asset custody service firm has developed a comprehensive framework, including issuance and management systems. BDACS has also developed an app that supports peer-to-peer transfers and transaction verification.  Each KRW1 token will be fully collateralized with South Korean won held in escrow at Woori Bank, the company’s strategic partner. BDACS believes that real-time banking API integration will ensure transparent, verifiable proof of reserves and reinforce trust and accountability within its network. The report revealed that Woori Bank also participated in the POC. BDACS acknowledged that it aims to position KRW1 as a universal-user stablecoin for remittances, payments, investments, and deposits. The Korean firm…
Share
BitcoinEthereumNews2025/09/18 17:29